Former executive chairman of the Urban Development Corporation (Udecott) Calder Hart may have made a bad decision. The decision may cost him close to $1 billion. This is the hefty price the former Udecott boss may have to pay for the award of multiple contracts for work at the controversial Brian Lara Cricket Academy in Tarouba by construction company Hafeez Karamath Ltd (HKL)
The company was contracted to carry out construction work on bid packages two, three, five and eight at the academy on December 12, 2006. The contract was valued at $242,822,500. The academy was one of the several mega-projects undertaken by Udecott under the former administration. It was expected to host the 2007 Cricket World Cup.
Nine years later, the water-soaked academy is nowhere close to being completed. The State claimed Hart ought to have known better. Hart, who now lives in Newriver Drive, East Fort Lauderdale, Florida, has eight days to file an appearance and 28 days to file a defence. Total payments, including advance payments, made to HKL are listed as $888,730,334.50.
Advance payments allegedly made to HKL amount to $400,838,120. Outstanding balance: $65, 680,978.88 Lead counsel Vincent Nelson, QC, and attorney Gerard Ramdeen are representing the State. The State is contending Hart:
• Failed to adhere to proper procedures;
• breached his duty to the Udecott board; and
• concealed family ties in connection with the Ministry of Legal Affairs Tower.
The works:
• PK Three: All interior and exterior finishes, vertical transportation, plumbing, fire protection, air-conditioning, electrical and audio visual.
• PK Five: Scoreboard.
• PK Six: Roof canopy.
• PK Seven: Sewage storage facilities, sports lighting, suites build-out (excluding stadium seats).
• PK Eight: Alternate/miscellaneous works - security fencing, food/beverage/concession area, additional retaining walls south-stand area, temporary roads/site facilities/security/safety, walkways and curbs.
A summary of the State's claim:
• At board meetings in 2006 Udecott entered into a contract with HKL to carry out construction work on packages of the BLCA.
It said Hart ought to have known that due to HKL's lack of management expertise and financial viability, there was a high risk it would be able to complete the construction work on packages two, three and five to eight in the agreed period or at all, and the agreement should not have been made.
• Authorised advance payments were made to HKL when Hart knew and/or ought to have known that its financial viability and management, technical and construction capability were such that the advances should not have been made.
• The document claimed that before the contract for the construction of the Ministry of Legal Affairs was awarded to CH Development, there was failure and/or refusal and/or neglect to disclose to Udecott's board and/or the tenders committee the relationship between Hart's wife and directors of CH Development.
The breach of duty arising from the award of the contract in relation to the BLCA is outlined as follows:
• In or about October 2002, Udecott decided to reissue an invitation to tender for the construction of the Customs and Excise Campus Plaza Project, Port-of-Spain.
• The tendering process for the Customs and Excise contract was done by public tender and the board, under Hart's chairmanship, decided on a post-qualification approach for contractors.
• On May 5, 2003, Hafeez Karamath wrote to Hart, as chairman of Udecott, to complain about questions Udecott asked of him and HKL on:
(a) Financial and accounting concerns and issues raised by Udecott representatives;
(b) general management and organisation concerns and issues and in particular the lack of evidence that HKL had a contract with a major sub-contractor; and
(c) HKL's financial capability to undertake the project.
Despite those warnings, on October 2, 2006 HKL was given a letter of award for the packages. According to the claim, HKL presented a payment certificate re-date to October 2, 2006 which reflected a new contract sum of $379,000,000 and a total advance payment of one per cent, being $68,566,986. Udecott also issued a payment to HKL of $53,898,135 guaranteeing the repayment of the advance in the event HKL failed to fulfil its obligations under the contract.
