NIDCO president speaks
President of the National Infrastructure Development Company (Nidco) Dr Carsen Charles has apologised for not providing more information on the technical aspects of the $7.5 billion highway which sparked the hunger strike of environmentalist Dr Wayne Kublalsingh. His apology came hours before Works Minister Emmanuel George meets with the Joint Consultative Council today.
Addressing the media at the Campden Heliport in Couva yesterday, Charles provided a report to the media, outlining details of the controversial segment of the highway. Media workers were taken on a helicopter aerial tour of the highway which weaves away from the Oropouche swamp, through several communities on the periphery of the Oropouche basin.
After weeks of waiting in vain for a cost/benefit analysis, social impact assessment and hydrological report, Charles revealed that works from Debe to Siparia are currently being withheld to allow Nidco to work through acquisition challenges.
"We were not ready for the extent of the bacchanal and we should have had people talking about the technical aspect of this report long ago...People feel we don't have any documents but this is not so," he said as he pulled out a multi-volume report titled, "Final report on Feasibility and Engineering Volume 1- 4.
The report included a copy of the Certificate of Environmental Clearance, granted in 2005 as well as paragraphs concerning flooding, community destruction, traffic impacts and integral benefits of the highway. However, he said professionals in T&T never took the opportunity of providing alternatives for the highway but instead chose to make complaints long after designs were completed and contracts were signed.
"When the opportunity presented itself, these professionals never made any complaints so they are guilty as well, just as we are guilty of not providing the technical reviews long ago," Charles said. Giving a financial breakdown of the costs, Charles said the main contractor OAS Constructora will be paid more than $5.2 million.
The entire highway will be built at a cost of $7.5 billion. He added that when cement prices went up, material costs of the highway escalated but the Government sought to protect the Treasury by signing a provisional "escalation cap" so that the contractor would absorb mounting price increases.
"Under the contract, OAS is fully responsible for executing the design of the entire highway. OAS has employed a highly respected international consultant HALCROW to prepare designs that satisfy the contract," Charles said. He also said extensive studies were done on the wetlands and out of three routes, the current one was most economical.
"We would get our chance to show everything in court. We are not a reckless and destructive people. We were all willing to talk and exchange ideas. We are not destroying the wetlands, we are building on the periphery of it," Charles said. He noted that a lot of misinformation was being bandied about. Holding up a newspaper clipping of a declaration by Government that the highway will bring 27,000 jobs, Charles admitted that this figure was "a little too high."
"This highway is the only thing that is happening now to fuel the construction industry. You think a hydrology study can be done in two months? Are we supposed to do a new one when it will take another year to do another impact report?" Charles said.
He also revealed that the Point Fortin phase of the highway had already started as Nidco had already paid $50 million to Petrotrin to cap oilwells. "We have 33 wells that must be capped and this project is under way so for those who are saying the highway will never reach Point, this is not true," Charles said.
He said the acquisition process was most challenging. However, he noted that 174 acres of land were provided in Petite Morne, Ste Madeleine to accommodate communities. Nidco's senior project manager Earl Wilson said the existing South Trunk Road would be upgraded to a four-lane highway and the Gordineau Bridge will be rebuilt.
Director of the Environmental Health and Safety Unit Doorlal Ramlal said previous alternatives proposed by residents would have landed "smack in the lagoon." He also noted that the Banwarie historical site or the Namdevco market will not be affected by the highway. He said the current route weaves through the least populated areas and the seven interchanges will bring connectivity to the people of south Trinidad.
MORE ON HIGHWAY
The project involves construction of four-lane divided highway. It will be done in several phases.
These included:
• Golconda to Debe which involves the building of 5 km from Golconda to Debe
• Debe to San Francique Road
• San Francique to Fyzabad Interchange
• Fyzabad Interchange to La Brea Connector
• La Brea Connector to Dunlop Roundabout
• Dumfries Road to Paria Suites
• Paria Suites to St Mary's Junction
• St Mary's Junction to Mon Desir Interchange.
