Lead Editor Investigations
asha.javeed@guardian.co.tt
NiQuan does not have authorisation from the Ministry of Energy and Energy Industries (MEEI) to restart its plant.
In a statement yesterday, the company said it provided two reports to the MEEI in the expectation that it would be cleared to re-commence operations—an Independent Root Cause Analysis Report dated August 19 on the incident at the plant on June 15 which led to the death of 35-year-old pipefitter Allanlane Ramkissoon and a copy of an Occupational Safety and Health Authority (OSHA) Certificate of Compliance dated August 23.
But the MEEI insists that its own investigation into the incident is not complete and the company is not authorised to restart the plant.
The Ministry’s Permanent Secretary wrote to NiQuan on August 28 and explained that the company still has outstanding documents to provide to the MEEI for it to complete its investigation.
The letter continued: “Further, we note that NiQuan Energy Trinidad Ltd (NETL) is of the view that the June 15, 2023 incident does not qualify as a major incident involving serious damage to the installation and thus no clearance for the recommencement is required from the MEEI. The MEEI advises that NETL’s view is incorrect and MEEI clearance for recommencement is required.”
NiQuan was advised that pursuant to the Petroleum Act Chap 62:01 and the Petroleum Regulations, the MEEI has started an investigation into the June 15 incident.
“The MEEI’s investigation has not been completed and as such, NETL does not have approval from the MEEI to recommence operations,” the letter said.
Gill blames Government
In the statement, Ainsley Gill, the company’s founder, chief visionary officer and director, noted that the NiQuan GTL plant “is completely functional, and ready to operate at capacity today.”
“Following NiQuan’s full compliance with the prohibition notice issued by the Occupational Safety and Health Authority and Agency (OSHA) on June 21, 2023, OSHA issued a Certificate of Compliance on the August 23, 2023, and physically removed the notice on the August 27, 2023,” the statement said.
Gill said: “The only reason the facility is not currently online is due to the lack of the minimum daily quantity of gas supply which the Government of T&T—through Trinidad and Tobago Upstream Downstream Energy Operations Company (UD)—agreed to provide to NiQuan pursuant to the Government’s contractual obligation to source and secure such required quantities of gas to keep the plant operational.”
On August 21, NiQuan lost a legal battle against the State in its bid to buy natural gas for the plant. For its part, the Government terminated the contract because NiQuan owes it US$21 million.
“Whilst NiQuan is looking to working with the Government to arrive at an amicable resolution, we must preserve our legal remedies pursuant to the gas sales contract terms, to protect the company and its numerous investors and stakeholders,” Gill said.
NiQuan has filed an appeal to compel the Government to give it gas to operate its plant.
“If the parties fail to resolve the matter amicably then, whether or not the interim injunctive and declaratory reliefs are granted following the Appeal hearing, the matter may ultimately be referred to ICC Arbitration as prescribed under the gas sales contract.
“Further, NiQuan has engaged Baker & McKenzie LLP in London and New York, and leading commercial King’s Counsel Stuart Isaacs KC of Wilberforce Chambers, to initiate the mediation process; and also, if no resolution can be agreed, to have oversight of all parallel legal and international remedies pursued against UD and the GORTT,” the company said in a statement sent to Guardian Media two weeks ago.
Niquan’s contract with the TTUDEOCL is for 31 million standard cubic feet per day (mmscf/d), or less than one per cent (approximately 0.8 per cent) of the T&T’s daily gas supply.
On July 30, the Sunday Guardian exclusively reported that NiQuan has more than US$250 million (TT$1.7 billion) in debt and is struggling to meet payments to the tune of millions owed to contractors, including Junior Sammy and Massy Energy.
NiQuan was set to refinance its bonds in the sum of US$300 million (TT$ 2 billion) by July 31, but the accident at the plant set it back.
