RADHICA DE SILVA
Senior Multimedia Reporter
radhica.sookraj@guardian.co.tt
Proman is investing approximately TT$270 million in a major turnaround at its AUM downstream complex at Point Lisas, involving more than 2,500 workers over 34 days.
The exercise began on November 4 and involves the temporary shutdown of the complex’s urea, urea ammonium nitrate (UAN) and utilities plants for inspections, maintenance, repairs and equipment upgrades. Production is expected to resume on December 9, with work progressing according to schedule.
During a media briefing and tour yesterday, Turnaround Manager Teressa Martinez said the work was critical to ensuring the plants operate safely and reliably until their next planned turnaround in 2029.
The exercise involves more than 1,300 jobs across the three facilities and requires about 1,800 people during peak daytime operations. Including night-shift workers, the site workforce is expected to reach between 2,500 and 2,700 during peak periods.
More than 70 local companies have been engaged, with about 52 per cent of the expenditure expected to benefit the local economy. Proman expects approximately 1.5 million man-hours to be expended during the planning and execution phases.
Major engineering work includes repairs to a nitric acid storage tank that had been operating at 44 per cent of capacity. Restoring the tank is a priority because nitric acid is a key input in UAN fertiliser production.
The company is also inspecting and maintaining the stripper unit in the urea plant’s ACES loop and replacing a 26-tonne expander unit on the UAN plant. Martinez said the expander was being replaced for the first time since the complex was commissioned in 2009.
The three facilities are interconnected, requiring careful coordination. The urea plant produces liquid urea, which is transferred to the UAN plant and combined with ammonia and nitric acid to make fertiliser for export. The utilities plant provides raw water, cooling water and steam.
Martinez said the turnaround had recorded no major incidents or accidents. The initial phase involved shutting down the plants, purging equipment and preparing the facilities for maintenance. Workers are now conducting inspections and assessments, with overseas technical support, including from Toyo, the process designers for the ACES loop.
The final phase will include pre-commissioning, inspections, integrity checks and functional testing before the facilities return to operation.
The company has also established procedures for managing waste, including metal, effluents and spent catalysts, in accordance with disposal and recycling requirements.