Senior Reporter
kevon.felmine@guardian.co.tt
Nearly $677 million has been spent on incomplete school projects across T&T, with several sites abandoned, overgrown and, in one case, non-existent, according to the Auditor General’s 2025 report.
The Auditor General has recommended that funding be prioritised to complete stalled projects and that monitoring systems be strengthened to prevent further delays, warning that without urgent intervention, public funds will continue to be tied up in unfinished infrastructure while schools and communities are left without basic facilities.
The findings in Chapter Four of the report paint a troubling picture of stalled infrastructure, weak oversight and poor project execution within the Ministry of Education’s school construction programme. A list of five stalled projects alone accounts for $116 million in expenditure, yet all remain incomplete, with progress as low as 11 per cent.
At the Iere Village Early Childhood Care and Education Centre, just 13 per cent of works were completed despite more than $3.1 million already paid. Auditors found the foundation overgrown and unsecured, with no action taken after a formal notice was issued to the contractor. The contractor’s bonds have since expired, with termination recommended by a consultant.
A similar situation exists at the Piparo Presbyterian Primary School, where $5.5 million was spent for just 12 per cent completion. The site was also found overrun with vegetation, with only basic foundation works completed.
The most significant project flagged was the new Parvati Girls’ Hindu College in Penal, where over $103 million has been spent, and works reached 72 per cent completion before being halted. The project has been suspended since August 2015.
The Ministry of Education attributed the delays to late payments to the contractor, which led to repeated work stoppages. The report noted that more than $13.8 million is still owed, alongside an ongoing breach of contract matter.
At the Upper Penal Rock Road Early Childhood Care and Education Centre, auditors reported that no identifiable structure exists, despite $2.27 million being paid. The ministry said components were fabricated off-site.
Meanwhile, the Maracas Bay ECCE Centre, with just 11 per cent completion, remains stalled but is expected to resume in the 2025/2026 fiscal year pending funding. The ministry said designs have been revised and approved.
The Auditor General noted a recurring pattern across projects: unsecured sites, heavy overgrowth, poor contractor performance and weak follow-up after corrective notices were issued.
The report also highlighted issues under the School Vacation Repair Programme. At Couva East Secondary School, auditors observed deteriorating infrastructure, including broken gutters and rotting window frames, even as the school remains in use. The ministry said repairs are scheduled for the July/August 2025 vacation period at a cost of $400,000.
At Holy Name Convent in Point Fortin, auditors found no evidence of a recently constructed annex, despite payments exceeding $3.3 million. The ministry responded that a prefabricated structure had been installed instead.
In light of the findings, the Auditor General called for a complete overhaul of project planning and execution, including prioritising projects based on community needs and addressing the growing backlog before starting new works.
Guardian Media sought comments from the Ministry of Education, the Unified Teachers Association and the National Council of Parent Teachers Association and is awaiting responses.
