Minister of Works and Transport Rohan Sinanan says designs for the repairs to the Manzanilla-Mayaro Road are complete, and a note is currently before Cabinet for its approval.
Sinanan told Guardian Media yesterday that the Ministry of Works and Transport should invite tenders for the road construction project in the next two weeks. Once the process goes well, work should begin within a month or month and a half.
Portions of the Manzanilla/Mayaro Road crumpled last November under heavy rainfall and intense flooding, causing the Ministry to close the road. Residents had to use longer alternative routes to get to and from their homes.
The ministry built a 10 km bypass road costing $14 million to restore traffic flow. In 2014, water from the Nariva River spilt over the roadway, washing away chunks of asphalt, resulting in the ministry building a new section. Despite missing out on the Dry Season to carry out the work, Sinanan said it was a project that needed a proper design.
“What we were hoping and still hoping will happen was that before the downpour of the rainy season, we will be able to get off the ground. It is not something that you could have just gone in and started to do work. You had to do designs. You had to do studies. You had to do consultations before you actually started the project,” Sinanan said.
With weather patterns changing significantly in the last decade, Sinanan said the ministry considered this when identifying weaknesses in the roadway to rectify with this project.
He said the plan is to build a resilient road, but people must accept that it is in a challenging area, with the Nariva Swamp occupying 225,000 acres draining on one side and the sea creating havoc on the coastline.
Sinanan said that when the ministry completes the repairs, there will be a continuation of the study to see how it can continue to improve the area to withstand harsh weather.
While work continues on the Solomon Hochoy Highway Extension to Point Fortin, a contractor was yet to repair a portion of the northbound carriageway along the Mosquito Creek, South Oropouche, which collapsed in January 2022.
While the Creek remains open, the Ministry redirects the traffic flow onto the southbound lane for several hundred meters. Sinanan said the ministry also had to do studies on that area.
“My information as early as today was that everything was completed.
The solution has been found, and they are actually finalising the new design for what has to be done to the area. They are finalising that, and work will resume on that part of the failure shortly.”