A couple from South Oropouche has settled their lawsuit over the acquisition of several acres of their land for the construction of the Solomon Hochoy Highway extension to Point Fortin.
The couple, who this newspaper agreed not to identify based on their lawyers’ concerns that they may be targeted by criminals, was initially claiming $6 million in compensation but agreed to take up a $3.4 million settlement offer made the by the Ministry of Works and Transport earlier this month.
When their constitutional motion came up for hearing before High Court Judge Betsy Ann Lambert-Peterson, the consent order between the parties was entered and the case was withdrawn.
According to their lawsuit, the ministry notified the couple that it wanted to acquire four acres of their land, located along Lake Road in Mon Desir, in May 2012. The couple sued the State after the land was used and they were not paid.
The couple claimed that the chose the property as they wanted to get into a large scale agriculture business and the area had good soil.
The couple built a large greenhouse, dug several ponds for a tilapia farm and planted 1,200 citrus trees, which were inter-cropped with plantain plants.
“Due to the land that was available to us we took advantage of economies of scale. The greenhouse that was constructed was the largest in the area and we planned it that way. At the time that the lands were the subject of acquisition, our greenhouse was fully established, and we were supplying the entire market of farmers in the south-western area of the country,” the couple said in the claim.
They claimed that when the State took possession of the land and graded it, three acres of the land with 900 plants were cleared with one-acre being left behind untouched.
“My wife and I have been made to suffer the hardship of having our business ruined. What is left of the land that was not used for the highway, highlights what we have lost. The fruit trees have matured and produced fruit beyond our expectations but because of the actions of the State and not being able to secure the trees properly much of the crop was stolen. I have still been able to reap some of the crops, but the joy of harvesting only brings the pain of what we have lost,” they said.
The couple was represented by Gerald Ramdeen and Dayadai Harripaul.
Construction on the highway began in 2011 under the People’s Partnership administration. The project faced repeated delays through protest action by the Highway Reroute Movement and its leader Dr Wayne Kublalsingh.
Kublalsingh and the residents filed a lawsuit over the Government’s failure to consult with them prior to constructing the Debe to Mon Desir segment of the highway. The judgement in the case is still pending.
Construction eventually stopped due to issues with financing and Brazilian contractor OAS Construtora. The National Infrastructure Development Company (Nidco) has recovered almost $1 billion in arbitration with OAS.
The project has since been restarted with work on several key segments of the highway. The project is scheduled to be completed in December, next year.
