RADHICA DE SILVA
Senior Multimedia Reporter
radhica.sookraj@guardian.co.tt
Proman is hoping to conclude negotiations with the National Gas Company (NGC) shortly on future natural gas supply contracts, as the company prepares to capitalise on anticipated increases in gas availability from new energy projects expected to come on stream from next year.
Speaking during a media tour of Proman’s AUM downstream complex yesterday, Deputy Managing Director Giselle Thompson said discussions with NGC had been constructive, but stressed that certainty over long-term gas supplies was essential to the company’s investment and maintenance plans at its Point Lisas operations.
Thompson said the company was committed to maintaining its operations and preparing its facilities to take advantage of available gas supplies.
“I can talk in terms of Proman and that we are already in discussions with the NGC in terms of gas supply contracts going forward, and those discussions have been constructive and we look forward to concluding them shortly,” she said.
Her comments come as Trinidad and Tobago anticipates an improvement in natural gas supplies with several projects expected to contribute additional production from 2027.
These include the bpTT-operated Cypre development, the Mento project and the Manatee field, as the Government and energy companies seek to address declining gas production and improve supplies to the domestic petrochemical industry.
During the tour, the media got a first hand glimpse at a US$40 million (TT$270 million) 34-day turnaround at its AUM facility, which produces nitrogen-based fertiliser.
Thompson said the investment was necessary to maintain the integrity of the facilities and ensure they remained safe and reliable for years to come.
The turnaround began on November 4, with production expected to resume on December 9.
She said the company was also planning two turnarounds next year, subject to the successful negotiation of new gas supply contracts.
“Every year we have turnarounds scheduled. For next year, we are expecting to do two turnarounds. Again, all based on being able to negotiate new gas contracts with the NGC, because in order to do the turnarounds, we need to have some certainty around gas supply for the future years,” Thompson said.
Asked about the recent closure of Nutrien’s operations at Point Lisas and the wider challenges facing the petrochemical sector, Thompson said the departure of investors and closure of industrial plants were troubling developments.
“No one wants to see investors leave or certainly plants close. It’s not good for our country,” she said.
However, she maintained that Proman remained committed to Trinidad and Tobago.
“ We’re here to stay and we continue to work with all our stakeholders to make sure that we continue to operate,” she said.
Thompson said Proman’s products, including methanol, ammonia and urea ammonium nitrate (UAN), were largely exported because the local market did not have sufficient industrial demand to absorb significant volumes.
She said the company’s contribution extended beyond production, with its operations supporting contractors, suppliers and communities around the Point Lisas industrial estate.
For the current turnaround, more than 70 local companies have been engaged, while the workforce is expected to peak at between 2,500 and 2,700 people across day and night shifts.
Turnaround Manager Teressa Martinez said by the end of the exercise, Proman expects approximately 1.5 million man-hours to have been expended during the planning and execution phases.
Martinez said about 52 per cent of the turnaround expenditure was expected to benefit the local economy through the employment of contractors and the purchase of goods and services.
Among the major engineering works is the repair of a nitric acid storage tank which had been operating at only 44 per cent of its capacity.
She said the restoration was critical to UAN production, as nitric acid is one of the key raw materials used in manufacturing the fertiliser.
Martinez said the turnaround was progressing according to schedule and had recorded no major incidents or accidents.
The initial phase involved shutting down the plants, purging equipment and preparing the facilities for maintenance crews. Workers were seen conducting inspections, repairs and equipment upgrades, with specialist technical support from overseas teams
The final phase will involve pre-commissioning checks, equipment integrity assessments and functional testing before the facilities return to operation on December 9.
She said the company also had procedures in place to manage waste generated during the exercise, including metal, effluents and spent catalysts, in keeping with the relevant disposal and recycling requirements.
Proman Head of Corporate Communications Colin Greaves said the US$40 million turnaround was generating significant economic activity across the Point Lisas community, with approximately half of the investment expected to flow directly into the local economy. More than 70 local contractors have been engaged, while vendors, transport operators and businesses supplying equipment and services are also benefiting.
Greaves said the 34-day exercise was on schedule, with no major safety incidents or accidents reported by day 14. More than 1,800 workers are on site during peak daytime operations, with hundreds more arriving and leaving during shift changes. He said Proman was committed to working with local suppliers and contractors to complete the remaining 20 days safely.