Senior Reporter
Elizabeth.gonzales
@guardian.co.tt
The Blue Wave Harmony is preparing to soon leave Trinidad and Tobago, but the Government has yet to account for the full cost of chartering, repairing and replacing the 35-year-old cargo vessel.
A review of the charter agreement obtained by Guardian Media found that the Government agreed to pay US$700,000 to bring the vessel to T&T and another US$700,000 to reposition it in Continental Europe or the Mediterranean at the end of the charter.
The review also found that a provision allowing the Government to terminate the agreement based on accumulated periods of downtime was struck out before the contract was signed.
Now, four months after the vessel was replaced on the inter-island sea bridge, it is being advertised internationally for charter and possible sale, raising questions about whether taxpayers will have to foot another TT$4.75 million bill for its departure.
However, when contacted last week, Works and Infrastructure Minister Jearlean John said the Blue Wave Harmony was no longer an issue.
“I don’t know, I don’t pay attention to these things. The point is the Blue Wave was on contract, it had some work to be done, they sent a replacement vessel and that’s it. The Blue Wave is not an issue now,” John said.
On November 19, a recruitment advertisement published on the international maritime employment website SeaJobs by Russia-based IQrew Management LLC indicated that the vessel could begin operating between Costa Rica and Puerto Rico following repairs in Trinidad.
The company advertised for a third officer on a four-month contract, offering a monthly salary of US$3,050, with a proposed joining date of November 26.
“Ship got repair in Trinidad till end Nov-beg Dec and will trade Costa Rica-Puerto Rica than,” the advertisement stated.
Separately, Dubai-based maritime chartering platform Mariniz advertised the Blue Wave Harmony as available for charter off Port-of-Spain.
One listing indicated that the vessel could be available in Continental Europe or Gibraltar in early to mid-December. It also states:
“Vessel can also be made available for sale - price reduced (can guide).”
Guardian Media contacted Mariniz seeking information on when the vessel was advertised, its charter rate and whether a new agreement had been secured.
Managing director M. Mandegar responded last Wednesday but did not address those questions. Instead, he appeared to treat the correspondence as a commercial enquiry.
“We are in shipping and chartering,” he wrote, requesting details about the proposed trading area, charterer and capacity requirements.
“Or if you want to buy the RORO vessel please let us know.”
Guardian Media also examined the United States Coast Guard’s November 10 register of active Certificates of Financial Responsibility.
The register showed that a certificate for the Blue Wave Harmony became effective on November 9, under German vessel management company Kontor 17 MPM GmbH. It expires on November 9, 2029.
The certificate relates to financial responsibility for pollution liabilities in US waters. While Puerto Rico falls within US jurisdiction, the certificate does not confirm that the vessel has secured a new charter.
International vessel tracking records placed the Blue Wave Harmony in Chaguaramas yesterday morning. It has been there since September 30.
Cost to taxpayers
The charter agreement, dated December 18, 2025, names the Republic of Trinidad and Tobago, through the Ministry of Works and Infrastructure, as the charterer and Panama-based Trading Abroad as the disponent owner.
The Government agreed to pay US$25,000 (TT$169,500) daily, or approximately TT$5.09 million every 30 days.
The agreement was for an initial six months, with an option to extend it for another six months.
Two invoices issued by Trading Abroad on December 22, 2025, showed that the Government was billed US$1.59 million before the vessel arrived.
This included US$750,000 for the first 30 days of hire, US$140,000 in insurance premiums and US$700,000 to position the vessel in Trinidad and Tobago.
The contract also required a bank guarantee or deposit equivalent to 60 days of hire, valued at US$1.5 million.
Box 13 of the agreement states:
“Charterers to pay a ballast bonus for $700,000 along with the last hire payment in order to positioning the vessel at cont/med.”
Based on 365 payable days, the charter fees, initial insurance premiums and both positioning payments amount to an estimated US$10.67 million (TT$72.31 million).
That excludes fuel, port charges and several other operational expenses borne by the State. It also excludes any deductions for periods during which charter hire was not payable.
The daily charter rate is US$2,500 higher than that of the Cabo Star, which served the inter-island sea bridge for nearly nine years.
This represents an annualised increase of approximately TT$6.19 million in charter fees alone. However, the Blue Wave Harmony offered greater cargo capacity.
Termination clause removed
Under Clause 15, the Government is not required to pay charter hire for qualifying periods of downtime caused by damage, defects, breakdowns or repairs.
The agreement states that in those circumstances, “the Vessel will be off-hire for the time thereby lost.”
However, another provision dealing with the Government’s ability to terminate the agreement was struck out.
Clause 45(c)(ii) would have allowed the Government to terminate the charter if accumulated periods of qualifying downtime exceeded 25 per cent of the total charter period, unless another threshold was specified.
The Government retained the right to terminate the agreement if the vessel remained continuously off-hire beyond 20 per cent of the charter period.
It remains unclear who requested the deletion and why the Government agreed to it.
The Blue Wave Harmony experienced difficulties shortly after arriving on January 22. It sustained hull damage during berthing manoeuvres in Tobago on January 30.
The Port Authority subsequently engaged a 67-metre cargo barge for ten days to transport goods that could not be accommodated on passenger vessels.
When Guardian Media questioned John in February about the cost of repairing the vessel, she responded:
“No, I don’t have the cost of that.”
Nine months later, the final repair bill and the cost of the contingency arrangements remain unknown to Guardian Media.
International tracking platform MyShipTracking recorded 121 arrivals in Scarborough and 120 in Port-of-Spain over the preceding year. However, Guardian Media could not independently establish how many were completed commercial sailings.
Problems with the replacement
On July 24, the National Infrastructure Development Company Limited (NIDCO) announced that the Blue Wave Harmony would be replaced by the Golden Carrier while maintenance and upgrades were undertaken.
NIDCO assured the public that the replacement would come at no additional cost.
“The charter hire will remain unchanged, and the introduction of the new vessel will not result in any increase or additional cost,” NIDCO stated.
The Golden Carrier, built in 1986, is five years older than the Blue Wave Harmony. It was chartered for a further six months at the same US$25,000 daily rate.
However, the replacement vessel has not been without problems.
In July, Guardian Media reported difficulties involving trucks using the vessel’s ramp at the Scarborough port.
The Port Authority disputed aspects of the report, stating that a truck rolled backwards because its parking brake had not been engaged. It maintained that no one was injured and no vehicles were damaged in that incident.
On October 5, an electrical problem aboard the Golden Carrier caused smoke near the passenger area during a sailing to Tobago, according to international maritime tracking and incident reporting website VesselTracker.
Passengers were moved onto the deck while crew members addressed the problem. No injuries were reported, and the vessel subsequently completed its journey.
The Golden Carrier’s six-month charter is expected to run into January 2027.
The original agreement also provides for discussions on a further two-year charter, with an optional additional year.
Questions unanswered
Earlier this year, the Port Authority confirmed in an April 10 Freedom of Information response that it did not procure the Blue Wave Harmony.
“PATT did not have conduct of the procurement process which resulted in the charter of the Blue Wave Harmony,” it stated.
Last week, Guardian Media contacted the Ministry of Works and Infrastructure’s corporate communications department and was referred to the Port Authority.
After Guardian Media explained that the Authority had already confirmed it did not conduct the procurement exercise, the communications representative promised to respond. No response was received up to press time.
Questions were also sent to NIDCO, PATT, vessel manager Kontor 17 MPM GmbH, shipbroker M3 International Logistics Corp and IQrew Management LLC.
Among the questions were whether the State continued paying charter fees during periods when the Blue Wave Harmony was unavailable, who financed the repairs, whether additional positioning and insurance expenses were incurred and whether the Government would have to pay the US$700,000 departure fee.
Those questions remain unanswered.
Guardian Media has also not obtained the amended agreement governing the substitution of the Golden Carrier.
However, in its July 24 announcement, NIDCO said the substitution was being facilitated under the existing charter agreement and would not result in any additional cost to taxpayers.
“The charter hire will remain unchanged, and the introduction of the new vessel will not result in any increase or additional cost,” NIDCO stated.
It remains unclear whether that assurance extends to the cost of repairs, insurance and the repositioning of both vessels.