Government is probing the long overdue Scarborough Hospital the construction cost of which has jumped from almost $136 million in 2002 to $719 million currently–resulting in a of $584.1 million cost overrun.
And the new completion date for the hospital is now March 2011, nine years after work started. Health Minister Therese Baptiste-Cornelis and Tobago Development Minister Vernella Alleyne-Toppin gave the information in a update on the hospital's stranded status, during yesterday's post-Cabinet media briefing. Baptiste-Cornelis said Cabinet yesterday approved some $30 million to finish the hospital. Government, however, has mandated Attorney General Anand Ramlogan to launch a forensic audit of the project and also asked the Finance Ministry's central audit unit to immediately examine the project's financial requirements up to 2010 inclusive of the additional $30 million.
Baptiste-Cornelis said initial construction of the project started with NH Caribbean in June 2002 at a cost of $136 million. In March 2005, some 35 per cent was complete and NHIC was paid $155 million, she said. The issue, however, later entered arbitration proceedings which cost the state $18 million in legal fees, Baptiste-Cornelis said. She said Nipdec then awarded a contract to China Railway Construction Co (CRCC) for $477 million to finish the project. Another contract worth $16.8 million was awarded by Nipdec to Genivar in December 2009 for design construction and supervision of service. CRCC's scope of works included two additional buildings, air-conditioning and remedial works. Baptiste-Cornelis said that to date, CRCC was paid $252 million for completion of 72 per cent of the work and supplying equipment. Project management fees to Nidpdec was $11million. Based on all of the above, Baptiste-Cornelis said overall expenditure for the hospital was $449 million currently.
She said the original completion date was April 2010. However, only 72 per cent of the work was done. CRCC received an extension to September 2010 to have the additional work done. Baptiste-Cornelis said that in 2010, the ministry allocated $130 million for the project, of which $128 million was expended. This left a shortfall which necessitated the movement of money from one ministry fund to another to finish the project. Baptiste-Cornelis said, however, that Nipdec had indicated that an additional $240 million would be needed to complete the hospital. Alleyne-Toppin who said there were outstanding invoices on the hospital, added that Cabinet had agreed to fund the $240 million to complete the project and for the interest of the people. She said the hospital started in 2002 and had not been delivered to date. "And it has cost the State so much money...from $130 million originally to end up at an estimated $719 million–we have a cost overrun for the Scarborough hospital of $584.4 million," the minister said.
"The Cabinet has agreed that the project will not be halted due to the audit. The building will be continued so that healthcare can be continued." Baptiste-Cornelis said the ministry would do an audit of the financial planning, liaising with the project management team to get an assurance on the "moving deadline" for the project. Alleyne-Toppin said projected completion date is now March 2011. "We hope to meet that deadline," she added. Baptiste-Cornelis said she could not say which contractor took the budget into cost overruns. She said the CRCC group has stuck to their budget. However, it was an addition of the "two" which contributed to cost overruns, she added. She said the Tobago Regional Health Authority also gave an estimate of $61.5 million for unfixed equipment. However, the ministry's team came up with another estimate of $38.8 million–$10 million of this coming from the Tobago House of Assembly. Baptiste-Cornelis said all of these "changing figures" were driving up the project's cost. Alleyne-Toppin said Genivar had also indicated that it had spend a lot of funds to replace a lot of pipes and other fixtures.
