JavaScript is disabled in your web browser or browser is too old to support JavaScript. Today almost all web pages contain JavaScript, a scripting programming language that runs on visitor's web browser. It makes web pages functional for specific purposes and if disabled for some reason, the content or the functionality of the web page can be limited or unavailable.

Monday, August 25, 2025

Teil awarded $50m for stillborn mega plant project

by

20120602

A US$219 mil­lion dol­lar claim filed by Trinidad En­er­gy In­vest­ments Ltd (Teil) chair­man Karl Hud­son-Phillips, QC, has been set­tled at US$8 mil­lion. The claim was filed in the Port-of-Spain High Court af­ter the for­mer ad­min­is­tra­tion failed to fol­low through with plans to sup­ply nat­ur­al gas to an am­mo­nia/urea mega plant at the Point Lisas In­dus­tri­al Es­tate.

It was in 2007 Hud­son Phillips, busi­ness­man Ger­ald Hadeed and at­tor­ney Garvin Si­mon­ette had ap­proached the for­mer ad­min­is­tra­tion with the busi­ness plan. Ap­proval was grant­ed by the Na­tion­al Gas Cor­po­ra­tion (NGC) and the busi­ness ven­ture went be­fore the Cab­i­net en­er­gy sub­com­mit­tee head­ed by for­mer prime min­is­ter, Patrick Man­ning and in­clud­ed for­mer en­er­gy czar Ken Julien and for­mer min­is­ters Lenny Saith and Con­rad Enill.

The plan was ap­proved by Cab­i­net and a Mem­o­ran­dum of Un­der­stand­ing (MoU) be­tween Teil and the for­mer ad­min­is­tra­tion was agreed up­on in 2005. The com­pa­ny, Teil, pos­sessed the on­ly va­cant 50-acre par­cel of land at the Point Lisas In­dus­tri­al Es­tate and to­geth­er with sport­ing fa­cil­i­ties was ex­pect­ed to fa­cil­i­tate am­mo­nia/urea plant.

Fol­low­ing the sign­ing of the MoU, Teil in­vest­ed some US$15 mil­lion to­wards the plant. The in­vest­ments in­clud­ed ne­go­ti­a­tions with in­ter­na­tion­al fi­nanciers from the Unit­ed States, Eu­rope and the far East. Hav­ing en­tered in­to the MoU, the for­mer ad­min­is­tra­tion and the NGC in­formed Teil that they would no longer be able to sup­ply nat­ur­al gas need­ed for the sup­port of the con­struc­tion of the plant.

An agree­ment to pur­chase the am­mo­nia and urea prod­uct was al­so in place fol­low­ing the com­ple­tion of the plant. As a re­sult, Teil is­sued a no­tice against the Gov­ern­ment for breach of the agree­ment. The fail­ure of the pre­vi­ous ad­min­is­tra­tion to abide by the terms of the MoU led to High Court pro­ceed­ings be­ing com­menced on be­half of Teil against the At­tor­ney Gen­er­al, NGC and the Na­tion­al En­er­gy Cor­po­ra­tion of T&T. In its claim, Teil stat­ed it had un­der­tak­en the fol­low­ing:

• Se­cured ap­pro­pri­ate land at the Point Lisas for con­struc­tion of the project

• Ob­tained a cer­tifi­cate of en­vi­ron­men­tal clear­ance to com­mence site prepa­ra­tion/con­struc­tion

• Reached an ad­vanced stage of en­vi­ron­men­tal im­pact as­sess­ment

As a re­sult of the fail­ure to pro­vide nat­ur­al gas for the plant, Teil claimed dam­ages in the sum of US$218,875,209.70 The com­pa­ny al­so claimed al­ter­na­tive dam­ages amount­ing to US$9,315,430.32. Ex­em­plary and puni­tive dam­ages for mis­rep­re­sen­ta­tion was al­so filed. At­tor­ney Mar­tin Daly, SC, and Ger­ard Ramdeen ap­peared on be­half of the State.