JavaScript is disabled in your web browser or browser is too old to support JavaScript. Today almost all web pages contain JavaScript, a scripting programming language that runs on visitor's web browser. It makes web pages functional for specific purposes and if disabled for some reason, the content or the functionality of the web page can be limited or unavailable.

Saturday, May 17, 2025

First gas from Touchstone delayed by two weeks

by

Curtis Williams
1085 days ago
20220525

Bad weath­er and ‘usu­al con­struc­tion de­lays’ are be­ing blamed for the two-week de­lay in first gas flow­ing from Touch­stone’s Co­ho dis­cov­ery which has now been pushed back to the mid­dle of June, ac­cord­ing to Paul Baay, the com­pa­ny’s Chief Ex­ec­u­tive Of­fi­cer.

In an in­ter­view with the Busi­ness Guardian, Bay was asked if Touch­stone will meet its pro­posed date to de­liv­er nat­ur­al gas to the Na­tion­al Gas Com­pa­ny (NGC) of May 30. He said, “We are not. We are prob­a­bly go­ing to be a cou­ple weeks late. We are shoot­ing for around the June 14 or 15.”

Once gas starts flow­ing from Co­ho it will be the first on land nat­ur­al gas de­vel­op­ment since the then British Gas start­ed pro­duc­ing from its Cen­tral Block.

Ini­tial­ly the gas com­ing from Touch­stone will on­ly by 10 mil­lion stan­dard cu­bic feet per day (mm­scf/d) but that is ex­pect­ed to be ramped up to 100 mm­scf/d by the time it brings on its Cas­cadu­ra de­vel­op­ment by the end of 2022.

“The next fa­cil­i­ty com­ing on, we’re look­ing at Oc­to­ber and that will start at 60mm­scf/d and should get to 90mm­scf/d by the end of the year, that com­bined with the 10 mm­scf/d that’s com­ing on in the next two to three weeks will get us to the 100mm­scf/d,” Baay added.

This will be wel­comed news for the coun­try which is in dire need of nat­ur­al gas and when it is ful­ly ramped up in 2023 could pro­vide enough gas for half of the coun­try’s re­quire­ment for elec­tric­i­ty gen­er­a­tion. It must be not­ed this is a new de­vel­op­ment and will be a net ad­di­tion to the coun­try’s oil and gas pro­duc­tion.

Baay ex­plained that Touch­stone is await­ing en­vi­ron­men­tal clear­ance and when that oc­curs he is hop­ing the pro­duc­tion out of its Or­toire block will get to as high as 200 mm­scf/d, with sus­tained pro­duc­tion over three to five years of at least 150mm­scf/d.

“We are on­ly bring­ing on the first two wells at our Cas­cadu­ra, that’s 90mm­scf/d. We are in the midst of putting in an ap­pli­ca­tion for an en­vi­ron­men­tal im­pact as­sess­ment which should come down in a lit­tle while, which should al­low us to drill eight more wells and those wells should al­low us to add an­oth­er 100 mm­scf/d. That should take us to about 200mm­scf/d. But cer­tain­ly we can main­tain at 150mm­scf/d,” he said.

Touch­stone’s CEO is hop­ing the com­pa­ny gets is en­vi­ron­men­tal clear­ance soon and ex­pects to drill the wells in ear­ly 2023 and have the ad­di­tion­al gas by the end of 2023.

He said, “Ba­si­cal­ly the ideas is to get up to that 180/200 mm­scf/d and then ba­si­cal­ly what you have af­ter that is we just drill to fill.”

What price will NGC

pay for Touch­stone gas?

But while the short­age of nat­ur­al gas is a ma­jor is­sue, so too is the is­sue of price. Baay said the price ne­go­ti­at­ed with the NGC was not as high as gas is be­ing sold for at the mo­ment, with no clause link­ing it to com­mod­i­ty prices like am­mo­nia and methanol.

“We have ne­go­ti­at­ed a price, we can’t dis­close this be­cause of con­fi­den­tial­i­ty agree­ments but yes we have ne­go­ti­at­ed a price.....Well it was ne­go­ti­at­ed dur­ing Covid so it is cer­tain­ly low­er than the gas price we are see­ing right now, but that was the deal and that’s the ben­e­fit of a long-term price that you get. You get the cer­tain­ty of the fixed price over four or five years, which is im­por­tant to us, be­cause we got a lot of cap­i­tal to spend, so it al­lows us to bud­get for that cap­i­tal.”

Not on­ly will the coun­try ben­e­fit from more gas but it is rich in liq­uids lead­ing to high­er crude pro­duc­tion via 2,000 bar­rels of con­den­sate a day and more op­por­tu­ni­ties for TTNGL.Asked about the Roys­ton dis­cov­ery which is light sweet crude oil, Baay not­ed that the com­pa­ny need­ed the funds from its gas pro­duc­tion to drill out the oil dis­cov­ery.

“If we could, we would like to drill it right away, but we want to wait un­til we got the gas on pro­duc­tion be­fore we move the rig. Just be­cause we need that cap­i­tal. We need rev­enue from the gas side to help us drill the oil side,” said Baay.

He added, “We think over the next cou­ple of years we should be able to get at least 5,000 bo/d. If com­bined with the con­den­sate and oil it will take us to 7,000 bo/d.”

In an in­ter­view ear­li­er this year Baay told the Busi­ness Guardian, “If you look at Pe­nal block, it has pro­duced over 100 mil­lion bar­rels of oil, and this is 1938 and it is ba­si­cal­ly a look alike to what we found at Roys­ton, like sim­i­lar depths, sim­i­lar type of crude, so I am not sure peo­ple ful­ly un­der­stand how sig­nif­i­cant the Roys­ton dis­cov­ery was.”

He was asked about the ex­tent of the fault­ing in the area which has made T&T no­to­ri­ous in its in­abil­i­ty to re­cov­er a lot of the oil it has dis­cov­ered with rates that range be­tween five per cent and 10 per cent on-land and off­shore be­tween 15 and 20 per cent, when the glob­al stan­dard is of­ten over 40 per cent.

“There is, and that is one of the beau­ties that we have of the seis­mic. We have got re­al­ly good res­o­lu­tion on it, there are some big faults but that struc­ture over­all, it’s kind of the same, again if you look at Pe­nal/Bar­rack­pore it is split in­to, call it sev­en dif­fer­ent fields, but it is still all in that same hori­zon, in that same ge­ol­o­gy struc­ture.

Roys­ton may end up be­ing that way where it is five or six dif­fer­ent fields but where it is over­all the oil we have en­coun­tered both in the over­thrust and in the in­ter­me­di­ate sheet are just fan­tas­tic, its beau­ti­ful low 38 Api oil, there is a huge de­vel­op­ment play on it, when I say hun­dreds of mil­lions of bar­rels, that’s oil in place so whether you want to put a 5 or 10 or 20 per cent re­cov­ery fac­tor on it, it kind of gives you a re­cov­ery fac­tor,” he added.

Jobs be­ing cre­at­ed

Baay said the de­vel­op­ment will lead to jobs be­ing cre­at­ed in the Rio Claro area with op­por­tu­ni­ties for op­er­at­ing both the Co­ho fa­cil­i­ty and the Cas­cadu­ra fa­cil­i­ty. There will al­so be a need for se­cu­ri­ty ser­vices, main­te­nance and op­er­a­tion.

Baay es­ti­mates at least 28 peo­ple will be em­ployed.