In spite of the cash flow challenges facing the Water and Sewerage Authority (WASA), the authority has injected a staggering $14.1 million investment into the controversial Beetham Gardens pipeline project which led to a fiery protest last month.
Public Utilities Minister Marvin Gonzales under whose purview WASA falls, admitted that this was the largest sum the authority had expended in the last two years to ensure the lives of hundreds affected in the Port-of Spain South constituency return to normalcy.
Giving a breakdown of the figures yesterday, Gonzales said, the authority has already spent $4.6 million since the project started last October.
“This was for rental of equipment, purchase of concrete cylinders and pipelines.”
When the project comes to a close on Friday (February 18) WASA would have forked out an additional $7.5 million.
“That would be to cover the remaining cost of heavy equipment, remedial works and materials such as road paving and these things.”
If WASA were to include the $2 million spent on internal labour, Gonzales said, the total cost of the Beetham Gardens pipeline project would be in the vicinity of $14.1 million.
The project required 47-inch diameter concrete sewer pipelines to be installed.
The authority also installed 624 feet of 44-inch diameter ductile iron pipelines which had to be buried at depths ranging from 19 to 26 feet.
Gonzales said this was the largest sum WASA has spent on a project in months, assuring that the new pipeline system will eliminate sewer backups and disruption and discomfort to residents.
“WASA has not undertaken a project of such a magnitude in the last two years. It was a massive project...the sewer that endangered the lives of the people of Beetham. I consider it to be money well spent.”
Gonzales said Sat Sais Company Limited was the main contractor that provided services to WASA.
“They provided most of the equipment for WASA.”
In January, an underground pipeline in the community collapsed, causing an overflow of raw sewerage and an offensive smell in the community.
The sewer line also caused a 15-foot-wide sinkhole on Main Street in Beetham.
Outraged by the incident, residents stage a fiery protest which resulted in an early morning traffic gridlock on the Beetham Highway and Priority Bus Route.
Police had to intervene to quell the protest, which Gonzales said, was fuelled by politics.
He also disclosed that the sewer that was flowing into the streets was a result of some elements in the Beetham community tampering with pumps the authority had rented to undertake works.
The elements were also accused of stealing diesel.
The theft of the diesel led to a breakdown of the pumps to channel sewer out of the community.
“Unfortunately sewer started spilling onto the streets,” Gonzales said, which triggered the residents to stage a fiery protest.
In addition to that, Gonzales said the project was faced with delays as a result of a lack of materials and a T&TEC employee being injured on the job site two weeks ago.
WASA had to receive an all-clear from the Occupational Health and Safety Authority to resume work.
Gonzales thanked the residents for their cooperation, patience and understanding.
He also praised WASA crews who worked “under severe challenges to get the job done. The health risk they were exposed to, I must commend them for their dedication and hard work. They must be applauded for going beyond the call. I know they missed their delivery timelines which were outside of their control.”