Senior Investigative Reporter
shaliza.hassanali@guardian.co.tt
Maintenance work on the Caroni Water Treatment Plant, which was completed 90 minutes ahead of schedule yesterday, cost the Water and Sewerage Authority (WASA) $5 million.
The figure was by Public Utilities Minister Marvin Gonzales, who said: “This was a major achievement for WASA knowing that we finished ahead of time.”
Gonzales admitted he barely got any sleep because he wanted to ensure everything was done according to plan. He said WASA was faced with challenges due to the weather.
At midday on Friday, the supply of water to approximately 500,000 customers was disrupted as the Caroni plant had to be powered down for repairs. WASA had advised affected customers that the planned three-day shutdown was expected to be completed yesterday.
The works undertaken were upgrades, regional maintenance and repairs on 23 projects. There were replacements to valves, pumps, transmissions and transformers.
The repairs were due to be completed by noon yesterday but Gonzales said by 10.30 am WASA had wrapped up the 23 projects. South’s transmission line was back in full service at 8 am while work on the north transmission was completed by 10.30 am “marking the end of the maintenance project.”
Gonzales thanked the 30 crews who worked around the clock along with WASA deputy chairman Alston Fournillier and senior executives.
He said during the shutdown there wasn’t an increase in calls for a truck-borne supply.
“What that demonstrated was that the population put the necessary measures in place. In that regard, I want to thank citizens for taking the planned shutdown seriously and allowing WASA to do their job,” the minister said.
With the plant back on the track, some communities began receiving pipe-borne water right away. However, customers in the furthest areas might experience longer delays before their service is restored.
“It may take between 24 to 48 hours for their supply to be returned. What we have done is keep WASA’s call centre in emergency gear and our trucks on standby should people need water in the next two days. We stand ready to assist,” Gonzales said, adding that this was the biggest WASA project to be undertaken during his ministerial tenure.
“It was to engage in active maintenance work to reduce the possibility of unplanned shutdown. The main purpose of the shutdown was to install several metres at our major transmission distribution system. This would assist the Authority to measure in real time the volumes of water going into particular areas so WASA can know when interventions are needed based on flows, pressures and volumes of water,” he explained.
The overall objective was to improve the reliability of the plant.
Gonzales said a significant component of the project was funded by an Inter-American Development Bank (IDB) technical cooperation grant which WASA received two years ago.
“That grant was to the tune of US$800,000 to install telemetric devices on our transmission and distribution system,” he said.
He said the IDB recognised that WASA had not been measuring the volumes of water it supplies to customers.
