In 2014, Tech Company Limited told would-be customers that if they bought land at their Central Springs Estates in Freeport, it would build all the infrastructure needed for land approvals within a year of purchase. But those who handed over their money, some from as far back as when the property was first advertised, are still waiting for the company to fulfill its promise.
“I took my retirement money and purchased land for my son when he got married so that he could start his family. It’s been three years and they’re still renting an apartment,” one landowner, who asked to remain anonymous, said.
Another said she purchased two lots in 2014 at $300,000 each.
“My husband and I were just starting out in life and this met our budget. We also knew that the developer had success in the past with the Riverview Park settlement in Longdenville, never in a million years we thought we’d end up in this situation.”
However, when Guardian Media visited the site along Raphael Road in Freeport on Monday, there was no sign of any contractor. A watchman alone patrolled the area, keeping a keen eye on our activities.
One of the company’s directors, Roshan Baboolal, subsequently contacted us to indicate the contractor would actually begin work next week. This was in contrast to what was said earlier by another company official, who declared work had started last week. Baboolal, however, assured that the infrastructural works to allow for approvals will be finished by January 2023.
But this does not mean approvals will be in hand by then, as the process for that will only begin on completion of the works. In Clause 12 of the sales agreement, Tech Contract Limited said those works entail the provision of infrastructural amenities such as roads, drainage, water, lighting and fencing.
Baboolal’s latest promise has, however, infuriated some of the landowners, who said they have heard this before.
“They are lying,” one woman said curtly.
Another lot owner said, “From 2015 to now, we have had little progress, leading owners to take out mortgages to build homes in another area, tying up financial assets in land which cannot be developed by us nor sold undeveloped.”
She forwarded an update sent in March 2022 by the company stating: “Management is working to ensure that the physical completion of infrastructural works (not approved application which may take a couple of months later) of the development is projected to be in September with the requisite approvals from the authorities prior to lot owners commencing construction activities.”
Asked about the reasons for the continued delays, Baboolal lay a large portion of the blame on the pandemic and the Water and Sewerage Authority (WASA).
“The development was going to be done in phases. Then prior to 2021, WASA changed its rules and they required the entire development to have fully completed infrastructure works before any approval can be given, these are their new post-COVID rules,” Baboolal said.
Baboolal said in the past, if a part of the project was complete, approval would have been granted just for that phase.
“Several developers are now going through this same problem.”
Baboolal said they are at the “behest” of WASA, as they are struggling to get the authority to come to the work site to inspect the progress. He said they are expected to recommence on September 15, 2022 and completion is set for January 2023.
“So, these things they are raising might be premature because we are already in August and next four- or five-months things will be completed, they’ve reached this far so maybe a little patience is needed.”
Baboolal said it was in the company’s interest to get the project finished, noting Central Springs is at the top of their priority list.
However, a source at the Couva/Tabaquite/Talparo Regional Corporation said two months is an impossible timeline for the approvals involved.
“The final approval they need to get is called Developmental Final Permit and that takes more than two months because they have to get approvals from drainage, fire and WASA and then we will have to send it to a department called CMOH that’s in the Ministry of Health and we have no control how long that will take there, and then it’ll come back to us and we have to do another round of site visits so they can’t say it’ll take two months, that’s more like four or five months at least.”
Guardian Media understands eight homeowners started legal action with a pre-action protocol letter sent on July 22 requesting damages and legal costs.
In a statement to Guardian Media, attorneys Varun Debideen and Stephanie Budram, who are representing the homeowners, said, “These people are without homes to call their own. In fact, some of them are even forced to pay rent for a number of years, which could have been monies used to construct their home all because they are not able to take possession of the lands. The developers continue to dismiss the purchasers’ pleas by providing generic annual updates.”
The company has been given until September 30, 2022, to complete works before legal proceedings begin.