Tobago Correspondent
The full opening of the new ANR Robinson International Airport in Tobago is getting closer to reality.
Minister of Works and Infrastructure Jearlean John said one of the key aspects of the $1.2 billion project nearing completion is the runway.
Speaking with Guardian Media on Monday, John said work is apace in Crown Point, but she will be visiting the island in two weeks for the possible substantial completion of the runway.
John said she will be accompanied by Minister of Transport and Civil Aviation Eli Zakour.
On March 15 last year, former prime minister Dr Keith Rowley, days before resigning, held a practical opening of the airport and toured the new terminal.
Former finance minister Colm Imbert was also optimistic that the terminal would be fully utilised in a matter of months.
“We expect, therefore, that barring unforeseen circumstances, the first plane with passengers can utilise this new terminal building in July 2025. We will all work together to make that happen,” he said at the practical opening.
However, John said there are many critical works still incomplete.
“The airport wasn’t opened. It wasn’t finished. You can’t open an airport if the runway isn’t finished.
“They are paving the runway right now. The work never stopped. The prime minister then would have accepted substantial completion of the building. You can’t have an airport without a runway, can you?”
John said the scope of work is no simple task and must meet international aviation standards.
“The paving has to be completed and then certified ... They don’t only report to the Civil Aviation Authority of Trinidad and Tobago. What comes into that certification is the Federal Aviation Association, because if something happens to a foreign airline here, then we are in problems, they will close it down.”
She said officials from the National Infrastructure Development Company (Nidco), which is managing the project, are in Tobago twice a week.
She said Nidco chairman Neil Dookie, a civil engineer, is taking a hands-on approach and is on site regularly.
“I get reports all the time. I have committed to go up there in about two weeks’ time with the Minister of Transport to see whether they could accept practical completion of the runway.”
She said there are other critical aspects of the project still to be completed, but anticipates those to be finished by early April.
Tobago tourism stakeholders are keenly looking forward to the airport being fully operational.
At a function last Friday to launch the Sixt Car Rental branch in Bon Accord, Tobago Hotel and Tourism Association, Reginald MacLean appealed for the opening of the airport.
The new airport has a capacity for three million passengers annually, and MacLean said he is eager to see the facility maximised.
“We need to get back to where we were in the early 2000s and late 1990s, where we had 95,000 international passengers to Tobago,” he said.
“The location they (Sixt) chose is perfect because the airport terminal is right next door. Mr (transport) Minister, we want it opened. I have been asking for that since you all got into office ten months ago, and we would like to see it happened. We don’t want it to rust and fall apart before we actually opened the facility.”
