Works and Transport Minister Rohan Sinanan says he was not happy about the communication between his ministry and the Water and Sewerage Authority (WASA) in relation to repair works that led to hours of traffic gridlock throughout west Trinidad over the last two days and well into last night.
According to Sinanan, while the emergency repair work near the Peake’s Service Station was necessary, the impact on residents and motorists in that part of the country on the Easter weekend was regrettable.
The traffic disruption came after WASA crews were forced to conduct emergency repairs on a ruptured 16-inch diameter pipeline near the Peakes Service Station, near the end of the Audrey Jeffers Highway, starting on Wednesday evening.
With the roadway heading west closed off during the work, the traffic gridlock extended into nearby areas such as Woodbrook, Mucurapo and St James, after motorists along the westbound lane of the Audrey Jeffers Highway had to be diverted away from the foreshore.
Guardian Media spoke with stranded motorists yesterday afternoon who all expressed their frustration over being stuck in the traffic.
“We’ve been here for over an hour and we haven’t moved anywhere. Works like this, it needs to be done in the night,” one angry driver said.
One motorist explained that she was forced to make alternate arrangements to have her children picked up because of the traffic jam.
Fish vendors in Cocorite also lamented the length of time to complete the works.
“Traffic whole morning, is time for it to move by now, I can’t even begin to talk about the losses as a result of this traffic congestion,” a fish vendor at the nearby Cococrite Fishing Facility said.
Speaking at a T&T Police Service vehicle handover ceremony yesterday, Minister Sinanan said the public should have been given timely notices of impending disruptions to avoid the type of inconvenience caused by the repair work.
“There was some level of miscommunication. I think when the work actually started, the ministry was not informed of the magnitude of the work. However, once we found out about it, the communications department at the ministry stepped in, the traffic management division stepped in,” Sinanan said.
“Unfortunately, I don’t think it is a situation WASA could have helped. I think going forward, we have to communicate in a much more quick fashion.”
Up until last night, major traffic gridlock was still reported heading into the west, as works were still being completed after WASA crews failed to meet several deadlines to complete the work it had given earlier in the day.
However, WASA explained that the repair works were hindered after workmen encountered high voltage electricity lines close to the ruptured pipeline. This rendered them unable to use the heavy equipment that would have speeded up the process.
Addressing the issue, Minister Sinanan also said WASA’s ageing infrastructure continued to pose obstacles for the public in several ways.
“It is unfortunate with what happened there and it is a challenge based on ageing infrastructure. It is one of the challenges we face when we do work in the city, you go in thinking that it is one line or two lines and then you bounce up things that you didn’t realise was there,” he said.
Sinanan assured that efforts would be made to improve communication and coordination between agencies going forward.
Late last night, WASA confirmed that while the emergency repair works had been completed, works to restore the roadway would take additional time. It said that work was to be completed by 8 pm but motorists reported no change in the gridlock.
“Motorists are asked to continue to proceed with caution and to obey the instructions of the Traffic Control Officers on duty, as final rehabilitation of the site is completed,” WASA said, also apologising for the inconvenience.