Senior Reporter
derek.achong@guardian.co.tt
The Water and Sewerage Authority (WASA) has emerged victorious in a protracted legal dispute with a contractor over the termination of a multi-million dollar pipe-laying contract.
In a judgment delivered yesterday, five Law Lords of the United Kingdom-based Privy Council upheld WASA’s final appeal over a decision by the local Court of Appeal to overrule a High Court Judge and order almost $14 million in compensation for Uniform Building Contractors Ltd.
The lawsuit centred around a specialist FIDIC contract, used internationally for civil engineering and construction projects.
Under the contract, valued at approximately $29 million, the company agreed to design, supply and install a total of 28.43 km of pipeline from Rio Claro to Mayaro.
The contract was eventually terminated by WASA in mid-2009.
Several years later, the company brought the lawsuit forward, before the statutory time limit for doing so elapsed.
The case was dismissed by High Court Judge Nadia Kangaloo but upheld by three Appellate Judges, including Chief Justice Ronnie Boodoosingh, in November 2023.
WASA filed a final appeal and retained Senior Counsel Anand Ramlogan and Ganesh Saroop, of Freedom Law Chambers, to pursue it.
In the judgment, the board ruled that the local Appeal Court was wrong to have upheld the company’s claims in relation to four purported variations to the original contract.
The variations included laying pipework in the roadway as opposed to verges, the removal of excavated material, the importation of suitable backfill, and being asked to work at night.
Sir Peter Coulson, who delivered the judgment, ruled that the Appeal Court erred in upholding the variations without referring to the terms of the original contract.
“Whether or not an item of work is a variation is primarily a function of the contract terms, so the absence of contractual analysis was, with respect, a fundamental flaw in their reasoning,” he said.
He also took issue with the fact that the Appeal Court’s decision was based on WASA’s engineer for the project approving the alleged variations.
“The Court of Appeal’s conclusion that, on the one hand, the engineer’s conduct did not amount to an amendment of the contract (which he was prohibited from agreeing) but that, on the other hand, the same conduct waived the relevant contractual requirements, failed to give full effect to the terms of the contract and is contradictory,” he said.
He also found issues with the Appeal Court upholding the company’s additional claim that even if the work was outside the contract, it should still be paid as WASA would benefit from services it did not pay for.
Coulson rejected the company’s claim that it was not aware that the additional work would be required when it entered into the contract.
“That argument must fail at every level,” he said, as he noted that it had several months before the terms were finalised to investigate conditions at the job site.
He also found that the purported variations were contemplated and provided for in the contract, and the company did not follow the proper procedure under the contract to claim additional funds.
“The purpose of the contractual regime was to ensure certainty so that, if there were claims for additional monies, they were clearly set out and promptly made,” he said.
WASA hailed the legal victory in a press release issued yesterday afternoon.
WASA CEO Dain Maharaj said the case set an important legal precedent for such specialist contracts.
“The decision to pursue this appeal is justified, and WASA is vindicated. The judgment will provide important guidance for all public authorities and is a landmark ruling that will usher in a new era of corporate governance based on principles of transparency, accountability and proper contract administration,” Maharaj said.
Ramlogan also issued a statement highlighting the legal issues decided in the case.
He said in the lawsuit that WASA’s own engineer supported the contractor in the case in contravention of the contract.
Stating that the judgment should serve as a “salutary warning”, Ramlogan said: “Contractors who do business with public authorities must think carefully about their practices.”
“Informality, procedural shortcuts, and collusive conduct— whether deliberate or reckless—have no place in public procurement,” he added.
He pointed out that the case highlighted the need to abide by written contracts.
