A construction company has lost its final appeal over almost $12 million in additional fees for a project it completed for the Urban Development Corporation of T&T (Udecott) two decades ago.
Delivering a judgment, yesterday morning, five Law Lords of the United Kingdom-based Privy Council rejected Dipcon Engineering Services Limited’s appeal against Udecott.
In the appeal, Dipcon claimed that High Court Judge Ricky Rahim and three Court of Appeal judges were wrong to dismiss its claim in 2017 and 2023.
The Board agreed with the concurrent findings of fact made by the local courts.
The lawsuit centred around a contract for engineering services for Oropune Gardens Phase II, a Housing Development Corporation (HDC) residential community in Piarco developed by Udecott.
The $26 million contract was signed in March 2003 and the work was completed in July 2006.
In 2009, the company and Udecott held discussions over settling the final accounts for the project.
Almost a year later, Udecott agreed to pay Dipcon $18,816,233.94 to settle its remaining claims in relation to the project.
However, Dipcon claimed an additional $11,255,800 as it contended that it incurred increased costs for using heavy equipment to complete its work.
Udecott’s Board of Directors refused the request as it claimed that it had factored in $3,500,000 for the increased costs when it made its total settlement offer.
Dipcon filed the case in which it alleged that there was no requirement for Udecott’s board to approve its additional request under the specialised FIDIC construction contract that was used for the project and is commonly used in international construction projects.
Dame Janice Pereira, who wrote the judgment, rejected the approval argument advanced.
“In the Board’s view, there is no room for arguing that board approval was either unnecessary or, as counsel put it, “a rubber stamp” exercise when the very wording of sub-clause 53.4 of FIDIC itself incorporates the taking of a decision by Udecott in circumstances separate and apart from the prescribed submission and payments procedure certified by the engineer set out under the contract,” she said.
She also rejected Dipcon’s alternative case alleging that the board approval requirement was waived by how it and Udecott conducted its contractual dealings.
“It is clear from the evidence establishing the parties’ course of dealing support by Dipcon’s own acknowledgement, that board approval was required before payment could be made,” she said.
Dame Pereira noted that she and her colleagues did not need to consider Udecott’s position on the case based on their rejection of Dipcon’s claims.
“After hearing Dipcon’s argument it became clear to the Board that Dipcon could not succeed on either of the bases put forward in its case,” she said.
Dipcon was represented by Tom Poole, KC, and Adam Riley. Ravindra Nanga, SC, John Paul Nahous, and Sasha Darbeau represented Udecott.