Kejan Haynes
T&TEC will commission the new Union/Gandhi 220 kV double circuit tower line on Tuesday. A statement from the Commission says the circuit will serve as a secondary backup to take electricity from Trinidad Generation Unlimited (TGU) in La Brea, to T&TEC’s transmission substation in Gandhi Village, "from where it will be distributed across the country. "
Last year residents filed an injunction to stop the construction since the line is passing through private properties in Siparia Old Road, Fyzabad. However T&TEC maintained construction of the circuit was vital.
“The circuit will reduce the likelihood of nationwide outages. On completion, the Commission will be able to transfer power to the new circuit to conduct outstanding maintenance work on the existing circuit which is over 10 years old and, in its current configuration, cannot be taken out of service for any significant period of time to allow preventative maintenance,” the Commission said at the time.
In August 2022, the 220-kilovolt (kV) transmission tower along the Union Estate-Gandhi Village partially collapsed because of a landslide, taking approximately 30% of customers across Trinidad offline.
Part of the line was also damaged by a falling tree in February 2022, causing the major nationwide blockout which kept the country in darkness for almost 12 hours.