Opposition Senator Wade Mark and Member of Parliament Dr Roodal Moonilal are being called upon to apologise to the people of T&T for divulging misleading information concerning the cost of construction works at the Prime Minister’s official residence in Tobago.
Urban Development Corporation of T&T (Udecott) chairman Noel Garcia made the call during a media conference yesterday, as he sought to clear the air regarding figures which have been quoted both by Mark and Moonilal.
Garcia said the allegations were made on August 26, 2019, where Moonilal called for a full independent enquiry into the refurbishment works at the Prime Minister’s official residence, saying that the project had jumped from two million dollars to $20 million.
Garcia said the UNC claimed earlier this month that the cost again increased from $25 million and jumped to $63 million.
“Senator Wade Mark, on November 14 in an article on the Trinidad Guardian, said the project jumped from $17 million to $42 million. On August 28, its budget was $25 million and the project cost never moved from $25 million to $63 million,” he said.
“Udecott never conferred any cost overruns. Udecott never certified any payments of $48 million and there’s no $15.4 million left unpaid.”
In a release earlier this month, Udecott advised that by virtue of Cabinet Minute No 2015 of February 8, 2018, approval was granted for: an estimated budget of $22,022,566.27 (VAT inclusive) for the construction of the Prime Minister’s Residence in Blenheim Road, Hope, Tobago, and that the Office of the Prime Minister, in consultation with the Ministry of Finance, had identified funds from its budgetary allocation to meet the expenditure referred to at 1 above.
It added that there was no project to “refurbish” the Prime Minister’s Tobago residence, nor was the budget $25 million. The approved sum of $22,022,566.27, which included Udecott’s project fees, was for construction works, not refurbishment works.
The contract was awarded to Parks International Limited in the sum of $20,305,020.
During the progress of the works, additional security measures were identified as requirements for the residence and this resulted in a variation to the contract in the sum of $8,150,131.86 VAT inclusive. As a result of the variations, the construction cost was revised to $36,552,181.
Noting that Udecott did not incur cost overruns that resulted in a revised project cost of $63 million and there are no sums outstanding to the contractor, Garcia called on Mark and Moonilal to apologise.
“Dig deep into your conscience, into your heart and find the strength to apologise because we have demonstrated that what you are saying is not true,” he said.
Twenty-six days for Red House ceiling repairs
Garcia also used the opportunity to dispel suggestions that the ceiling of the Red House’s North Chamber had collapsed last week.
“The Red House ceiling did not collapse and we sent out a news release that a piece of moulding became detached from the ceiling because of condensation,” he said.
During a visit to the Red House on Tuesday, Garcia said the technical staff was embarrassed by the “lack of technical knowledge of Senator Wade Mark when he said the ceiling collapsed so the structural integrity of the building is in jeopardy. The ceiling never collapsed.”
Garcia said remedial works are currently underway and should be completed in 26 days’ time.