A potential solution to the erosion and seasonal flooding issues experienced at Pigeon Point and Milford Bay in Tobago is closer in sight.
That assurance came from the Division of Infrastructure, Quarries and Urban Development, in the Tobago House of Assembly (THA).
The Division’s Coastal Zone Management Unit (CZMU) indicated that in early March 2022, Smith Warner International began work to conduct a Comprehensive Coastal and Environmental study as part of a longer-termed effort to mitigate further damage to the coastline of the tourism and business hotspots.
A complete Ecological Assessment Report is due in August 2022.
As part of the Study, four Acoustic Doppler Current Profilers (ADCP) were placed at key points on the south-western coast of Tobago.
These profilers measure coastal conditions inclusive of waves, currents, tides and water levels.
Last week, those four profilers were retrieved from the ocean and the process of downloading and analysing the data has begun.
One additional ADCP was re-deployed on the outer reef to be able to capture wet and dry season data for the next four months.
Essentially, the data gathered from these profilers will then be used to design potential nature-based solutions, to mitigate existing conditions and build coastal resilience against erosion and flooding in the area.
Project Manager of Smith Warner International, Edward Albada, said
“This is all exploratory and investigatory work with preparation for a better understanding of coastal processes, which will then feed into various solutions that we are looking for.”
In October 2019, significant damage was done to the coastline and commercial structures along the Pigeon Point Heritage Park.
The current studies supplement temporary emergency stop-gap measures done by the Division.