JavaScript is disabled in your web browser or browser is too old to support JavaScript. Today almost all web pages contain JavaScript, a scripting programming language that runs on visitor's web browser. It makes web pages functional for specific purposes and if disabled for some reason, the content or the functionality of the web page can be limited or unavailable.

Wednesday, August 27, 2025

T&TEC hopes customers reduce electricity use during TGU shutdown

by

644 days ago
20231122
T&TEC general manager  Curvis Francois

T&TEC general manager Curvis Francois

Re­porter

kalain.ho­sein@guardian.co.tt

T&TEC gen­er­al man­ag­er Curvis Fran­cois hopes cus­tomers will re­duce their elec­tric­i­ty load from Sat­ur­day night in­to Sun­day morn­ing when Trinidad’s largest pow­er gen­er­a­tion plant will be tem­porar­i­ly of­fline for crit­i­cal up­grade works.

“Any form of con­ser­va­tion that cus­tomers could prac­tice dur­ing that pe­ri­od would be good,” he said.

The shut­down is ex­pect­ed to take place be­tween 10 pm Sat­ur­day and 9 am Sun­day, a pe­ri­od with low elec­tric­i­ty load across Trinidad. Fran­cois hopes cus­tomers will re­duce their use of high-en­er­gy-con­sum­ing ap­pli­ances.

“The biggest use would be air con­di­tion­ing load, and we would hope that cus­tomers would prob­a­bly cut back, turn­ing it on at night and come off in the wee hours of the morn­ing,” he said

Al­lay­ing fears of a re­peat of the Feb­ru­ary 2022 black­out in which the pow­er grid ex­pe­ri­enced a cat­a­stroph­ic fail­ure pre­cip­i­tat­ed by a falling tree branch on a high-volt­age cir­cuit, Fran­cois said: “I’d like to say that there is a very low like­li­hood of a black­out oc­cur­ring or any kind of na­tion­wide black­out oc­cur­ring as a re­sult of the TGU shut­down.”

Trinidad Gen­er­a­tion Un­lim­it­ed (TGU) pro­duces ap­prox­i­mate­ly 50 per cent of Trinidad’s elec­tric­i­ty. When that plant is tak­en of­fline on Sat­ur­day night, pow­er from two oth­er in­de­pen­dent pow­er gen­er­a­tors, Trin­i­ty Pow­er and Pow­er­Gen, will make up the short­fall.

The T&TEC gen­er­al man­ag­er said both plants will be suf­fi­cient to cov­er the load, but if one of the units at ei­ther plant suf­fers an is­sue or is over­loaded, load shed­ding might oc­cur.

“If there is load shed­ding, a small per­cent­age of our sys­tem would be shut down. If we lose a unit, we have enough spin­ning re­serve to cov­er that, but if there is any­thing more than that, we can have load shed­ding tak­ing place, af­fect­ing just a few thou­sand cus­tomers for a short time. We don’t con­sid­er it a huge risk to the sit­u­a­tion,” he said.

Fran­cois added that T&TEC serves more than 500,000 cus­tomers. T&TEC cus­tomers in To­ba­go will not be af­fect­ed by the TGU shut­down this week­end.