Senior Reporter
derek.achong@guardian.co.tt
A contracting company is appealing a judge’s decision to dismiss its $90 million lawsuit against the Tobago House of Assembly (THA) over unpaid fees and interest for an infrastructure project.
In the appeal, Raghunath Singh and Company Limited, through its attorneys led by Peter Taylor, is claiming that High Court Judge Frank Seepersad was wrong to have dismissed its case at a preliminary stage earlier this year.
Justice Seepersad’s decision was mainly based on the company’s delay in bringing the litigation, after its negotiations with the THA broke down years ago.
Referring to the provisions of the Limitation of Certain Actions Act, Justice Seepersad said, “This court is resolute in its view that all of the claimant’s claims commenced more than four years after the accrual of the cause of actions. Consequently, they are all statute-barred and must be dismissed.”
Despite his finding, Justice Seepersad still meticulously considered the merits of the company’s claims and rejected them.
“Having engaged in this manner of examining the evidence in this case, the court is resolute in its view that the claimant has failed to discharge it burden to prove on a balance of probabilities that the sums of money claimed as being due and owing to it are, in fact, due and owing,” Justice Seepersad said.
The lawsuit related to a approximately $40 million contract for the construction of the L’Anse Fourmi-Charlotteville Road.
In May 2002, the Central Tenders Board awarded the company the contract after a tendering process.
Under the terms of the contract, the company was required to provide a performance bond of ten per cent of the contract sum and complete the work within 18 months of the site being handed over.
The work was completed by the company in March 2007, as it claimed that the project was delayed by variations in designs by the THA, inclement weather, cost fluctuations, legislative changes and regulatory approvals demanded by the Environmental Management Authority (EMA).
It claimed that the final cost of the project was $58,280,366.36 and it was only paid $31,266,900.05. It also contended the THA retained the majority of the performance bond.
Through the lawsuit, the company was seeking the $27,053,466.31 balance and $53,464,548.62 in interest.
In defence of the case, the THA claimed the cost overruns claimed by the company were not properly submitted to its engineer for verification and approval under the terms of the contract.
The THA also claimed the lawsuit should have been brought against its chief administrator named in the contract and it (the case) was filed outside the four-year limitation period.
Justice Seepersad ruled that the THA was a proper party to the lawsuit as the project was for its benefit, was within the sphere of its statutory responsibilities and payments were made by it.
However, he upheld its claim in relation to the delay in pursuing the lawsuit and over the procedure used by the company to make the claims for the overruns.
As part of his decision, Justice Seepersad ordered the company to pay the THA $636,590,07 in legal costs, which was based on the value of compensation it sought in the case.
In the appeal, the company is claiming Justice Seepersad made errors in assessing the facts in the case and in applying the law in relation to the contractual dispute.
The company was also represented by Egon Embrack, and Nehanda Samuel.
The THA was represented by Russell Martineau, SC, Dominique Martineau and Avionne Thomas.
